Project
New Liquid Line brown field (Civil works)
A complex €25M brownfield industrial project involving the construction of a new liquid production line inside an existing operational factory. With only around 10% downtime, the project required precise coordination, basement reinforcement, piling works, steel structure erection, stability checks, and intensive site supervision to deliver a new production facility within a live manufacturing environment.
Scroll to explore

Brussels (BE)
2024-2025
Industrial Project
1. Project Overview
This project involved the creation of a new liquid production line within an existing and fully operational industrial facility in Halle, Belgium. Unlike a greenfield project, the works had to be executed inside a running factory, where production continuity, safety, access management, and technical coordination were critical from day one.
The challenge was significant: build new industrial infrastructure without stopping the surrounding operations. The project required a strong brownfield strategy, combining civil engineering, structural works, steel construction, and on-site coordination within a constrained production environment.
With a total project value of approximately €25 million, the works demanded a high level of technical preparation and execution control. Despite the complexity, production downtime was limited to approximately 10%, demonstrating the importance of planning, phasing, and hands-on site supervision.
2. Scope of Works
The scope covered several critical phases of the project, from structural assessment and civil works to steel erection and execution follow-up. The works were carried out in close coordination with the project partners and site teams to ensure safe and efficient progress inside the operational factory.
The scope included:
Brownfield construction strategy inside a live factory environment
Coordination with project partners and site stakeholders
Basement reinforcement works
Piling works and foundation-related interventions
Structural stability checks
Metallic frame erection
Integration of the new structure within the existing building
Technical follow-up of civil and structural works
Site supervision during execution
Coordination of works with ongoing factory operations
Planning support to reduce production interference
Safety, access, and execution control in a constrained industrial environment
A key aspect of the project was the ability to connect new construction works with existing infrastructure while maintaining operational continuity. Every intervention had to be carefully planned to avoid unnecessary disruption and to keep the production environment under control.
3. Result & Added Value
The project successfully delivered the construction support for a new liquid production line inside an existing factory, under challenging brownfield conditions. Despite the scale and complexity of the works, downtime was limited to approximately 10%, allowing the industrial operations to continue during most of the project.
The added value of this project lies in the ability to manage a difficult industrial construction environment where space, safety, planning, and production continuity were constant constraints. From basement reinforcement and piling works to steel frame erection and stability checks, the project required both technical expertise and strong field coordination.
This project demonstrates the capability to deliver complex industrial infrastructure in demanding brownfield conditions: building inside an operating factory, controlling risk, limiting downtime, and turning a highly constrained environment into a successful construction zone.
25 millions €
Total project cost
EPC contract
90%
Uptime
Downtime during oeprations due to Alimentary Regulations
9 months
Duration
Start to handover (Civil Works)
An insight into our work
Submit a project to our team
Send us your constraints and your deadline. We'll come back with a first technical read and a clear view of what the structure needs.
Subscribe to the newsletter
Occasional notes on structural design, Eurocode updates and the projects leaving our office. A few times a year, nothing more.