Project
High-Speed Revamping of 3 Industrial Cooling Towers
This project involved the revamping of three industrial cooling towers within a highly sensitive production environment. The works included the technical study, execution preparation, and on-site follow-up, with all three towers successfully revamped within one week while preventing debris from entering or interfering with the cooling system.
Scroll to explore

Brussels (BE)
2023
Industrial Project
1. Project Overview
The project consisted of the revamping of existing cooling towers on an operational industrial site. Due to the importance of the cooling system in the production process, the works had to be carefully studied, planned, and executed to avoid any impact on the installation’s performance.
A major challenge of the project was the execution within a very short timeframe. Three cooling towers had to be revamped in only one week, requiring precise preparation, strong coordination, and continuous on-site follow-up.
Special attention was given to the protection of the cooling system during the works. The execution method was developed to avoid any interference caused by debris, ensuring that the system remained protected throughout the intervention.
2. Scope of Works
The scope included both the study phase and the execution follow-up on site. The project required a detailed analysis of the existing situation, preparation of the intervention methodology, and coordination of the works to guarantee safe and efficient execution.
The works included:
Technical study of the existing cooling tower installations
Preparation of the revamping methodology
Planning and coordination of the intervention
Execution follow-up on site
Revamping of three cooling towers
Implementation of preventive measures against debris contamination
Monitoring of works to avoid interference with the cooling system
Coordination between technical requirements, safety constraints, and execution planning
The revamping activities were organized to ensure that the works could be completed within the available timeframe while maintaining control over operational risks.
3. Result & Added Value
The three cooling towers were successfully revamped within one week, without debris entering or disturbing the cooling system. This result was achieved through careful preparation, a controlled execution method, and close follow-up during the works.
The added value of the project lies in the combination of technical preparation, fast execution, and operational risk control. By anticipating the constraints of the cooling system and implementing protective measures on site, the project was completed efficiently while preserving the reliability of the industrial installation.
This project demonstrates the ability to manage complex revamping works in an operational environment, where planning, safety, cleanliness, and continuity of service are critical.
+15%
Increase in cooling capacity
By replacing used materials by new and more advanced materials
100%
Uptime
No downtime during oeprations
1 week
Duration
Start to handover
An insight into our work
Submit a project to our team
Send us your constraints and your deadline. We'll come back with a first technical read and a clear view of what the structure needs.
Subscribe to the newsletter
Occasional notes on structural design, Eurocode updates and the projects leaving our office. A few times a year, nothing more.